Ramelton, Milford and Rathmullan Sewerage Scheme
Wastewater Project
Uisce Éireann, working in partnership with Donegal County Council, is upgrading the wastewater network infrastructure in Ramelton, Milford & Rathmullan.
When completed, this project will reduce the risk of sewer flooding and address non-compliant sewer overflows into the Maggy’s Burn, Fawninoughan Stream, Carn Low, Rossreagh, Glenalla, Craigmaddyroe Far, Carraleena, Crevary Lower, Mill Brook, Ramelton & Lough Swilly.
It will also improve the capacity of the sewer network allowing for current and future population growth, and supporting the social and economic development of Ramelton, Milford & Rathmullan and the surrounding area.
These works will ensure the treatment of wastewater is fully compliant with EU Urban Wastewater Treatment Directives and Wastewater Discharge License Emission Limit Values and will eliminate all non-compliant combined sewer overflows within the area.
Murphy Ireland will carry out the works on behalf of Uisce Éireann.
Benefits
- Improved water quality in Leannan Estuary and Lough Swilly. This will remove the risk to the protected areas within Lough Swilly, including the Special Areas of Conservation (SACs), Special Protection Area (SPA), shellfish waters and designated bathing waters, including Rathmullan Beach.
- Removal of the discharge of inadequately treated sewage into Maggie's Burn will improve the water quality. It will also remove the risk to water quality in the downstream catchment of Lough Fern and the Leannan Estuary.
- Cleaner water will enhance the areas amenity value, particularly in Rathmullan which will contribute towards restoring the Blue Flag status of Rathmullan Beach.
- This project will improve water quality and potentially salmon spawning in Maggie's Burn which is a designated Salmonid Water.
- The new pumping stations and wastewater treatment plant have all been designed to accommodate an increase in the local population supporting future growth in each of the three towns.
- The project will ensure that the water quality standards set down by regulatory bodies such as the Environmental Protection Agency will be achieved
What is involved?
- Construction of a wastewater treatment plant that will serve a population equivalent of approximately 5,500.
- Decommissioning of the current underperforming plant in Milford, construction of a new pumping station at Milford and rising main to bring wastewater to the new plant.
- Construction of two pumping stations at Ramelton and Rathmullan along with a rising mains that will transfer wastewater to the new plant.
- Construction of a local pumping station in Rathmullan to transfer network flows to the new main pumping station in Rathmullan.
- Construction of a new outfall pipe from the new wastewater treatment plant that will safely discharge treated wastewater into Swilly Estuary.
- Decommissioning of two septic tanks in Rathmullan.
Works in Milford:
Start Date | Duration | Planned Works | Traffic Management |
---|---|---|---|
24th June 2024 | 12 Weeks | Groundworks and landscaping | No traffic management |
Works in Ramelton:
Start Date | Duration | Planned Works | Traffic Management |
---|---|---|---|
24th July 2024 | 10 Weeks | Pipework into the new pumping station tank and associated services to the site. | No traffic management |
30th Sept 2024 | 3 weeks | Installation of gravity sewer along the boundary of site on Castle Street | Traffic Management. Lights |
Works in Rathmullan:
Start Date | Duration | Planned Works | Traffic Management |
---|---|---|---|
12th August 2024 | 3 Weeks | Kerry Bay into PS2 fir the installation of services along with connection of the rising main | Traffic Management Traffic Lights |
09th September 2024 | 2 Weeks | Kerrs Bay, chamber construction for sewer diversion, and all other associated tie-ins | Traffic Management Traffic Lights/Stop & Go, at peak times |
10th September 2024 | 4 Days | Inspection of the rising main air valves and sluice valve chambers | Traffic Management Stop & Go |
Works in Tirroddy:
Start Date | Duration | Planned Works | Traffic Management |
---|---|---|---|
04th December 2023 | Ongoing | Variation of mechanical and civil works throughout the site. | No Traffic Management |
The Ramelton, Milford and Rathmullan Sewerage Scheme is carried out by Murphy Group on behalf of Uisce Éireann.
More information
For further information you can contact the Project Team at RMRwastewater@water.ie.