Skip to main content

Inishowen Regional Water Supply Scheme

Water Supply Project

This €5.8 million investment addressed the water quality issues in the Greencastle Water Supply by transferring water from the Pollan Dam Water Treatment Plant into the East Inishowen supply area.

These works enabled water to be supplied into the Greencastle area and allowed for the decommissioning and rationalisation of the Greencastle Water Treatment Plant.

Location
Donegal
Status
Completed
Investment
€5.8 million

Benefits

  • Improve drinking water quality
  • Secure safe water supply
  • Improve service levels

Steps

  • The transfer of 1,500m³/day from the Pollan Dam Water Treatment Plant into East Inishowen.
  • The construction of a pumping station within the existing Pollan Dam Water Treatment Plant site
  • 6.95km rising main to a new 1,000m³ reservoir at Crockaveeny and 4.5km of distribution main

View all projects and plans

Visit our Projects section to find out what's happening in your area.