January 2023 - December 2023


PreConnection Enquiries

Positively responded to 78% of enquiries within 16 Weeks
Icon

3,008

Positive Responses

Icon

98,369

Associated Housing Units

Icon

129¹

Refusals

Icon

409²

Associated Housing Units


Connection Offers

Issued 83% of offers within 16 weeks
Icon

4,597

Offers Issued

Icon

42,970

Associated Housing Units

Icon

144¹

Refusals

Icon

489²

Associated Housing Units


Connection Agreement

Icon

3,599

Connection Agreements Executed - Customer Signed & Paid

Icon

30.339

Associated Housing Units


Connections

Icon

6,634

Completed Connections

Icon

40,431

Associated Housing Units


Quality Assurance

Icon

8,228

Site Visits Complete

Icon

1,569

Non-Conformance Notices


Self-Lay in the Public Road

Icon

16

Positive Responses

Icon

928

Associated Housing Units

Icon

8

Refusals

Icon

773

Associated Housing Units


Planning Assessments

Icon

c11,347

Completed Assessments

Icon

c72,436

Associated Housing Units


Notes

  • ¹ Enquiries & Applications that did not meet the criteria for approval include both Domestic and Non- Domestic.
  • ² Majority of housing units associated with single houses or small housing developments.
  • ³ Stats above are based on current data and reporting practices.

Glossary

This means the physical connection of a Customer's Premises to the Network to facilitate the provision of Water Services to the Customer's Premises.

This means the written agreement signed between the Customer and Uisce Éireann setting out the commercial and technical terms governing the Connection.

This means a formal application made to Uisce Éireann for a Connection. The relevant Connection application forms can be found on www.water.ie.

This means all the infrastructure required to provide or facilitate the provision of the Connection.

This means the letter that is issued to the Customer by Uisce Éireann and which details the Connection terms and conditions (including the amount of the Connection Charge) that are offered to the Customer.

This means any party which has entered into a Connection Agreement, or applied to enter into a Connection Agreement, with Uisce Éireann. It also means any party which has entered into (or applied to enter into) a Diversion Agreement, a Build Over Agreement, or a Project Works Service Agreement.

Formal engagement by UÉ with Planning Authority highlighting in relation to planning application.

Communication from a Planning Authority to a Statutory Consultee to notify of developments that may impact upon them. Typically, this is an electronic email containing planning reference number and development details sent from the Planning Authority to UÉ.

Enquiring about the feasibility of a water and/or wastewater connection to Uisce Éireann infrastructure.

Field Engineers carrying out on site Quality Assurance on self-lay housing developments. This process is ensuring that IW vest quality water service assets for long term protection of homeowners.

Infrastructure will typically be constructed and paid for by the Customer and vested by Uisce Éireann is known as 'Self Lay'.

A notice issued when there is a significant non-compliance with the Connection Agreement, Codes of Practice or Standard Details arise during the construction of the development. These are rectified by the developer during the QA process.

UÉ, as a Statutory Consultee is obliged to respond to the Planning Authority and address any identified impact arising from the development in the context of provision of water and wastewater connection and/or protection of Drinking Water Sources.